Monday, December 30, 2013

Who put the Roof on..Who Who December 30, 2013

4 guys from JR Roofing came out today and put the roof on.   Took about 6 hours.  Each guy started in a corner.

Can't wait for the Cypress Creek Hemlock siding to be put on.


Garage door was put on also last week.














Friday, December 20, 2013

Electrical and HVAC - December 19, 2013

Both started on Wednesday when we did the walk through with the electrician. When we went back on Friday so my hubby could do the wiring for the surround sound, they said they would be done that day.  We will go back by on Monday to see the end result. It was a warm rainy day today-got up in the low 50's.

Thursday, December 19, 2013

Foyer view - December 19, 2013

Partial Kitchen Layout - December 19, 2013

Rough draft outline of the back side of the kitchen.  Counters, Frig and Stove.  I can't wait to see my cabinets in place!  My dilemma is what color to paint the walls!  I want contrast for my cream cabinets.  We still have to pick out the color of the granite.

Sunday, December 15, 2013

More inside pictures December 15, 2013

Looking a little like a home?!?!?! Come on in and take a seat. 
There was some extra tar paper that we cut to size to mimic our furniture.  This way we could place our floor outlets easier.




Inside Framing December 15, 2013

Dining room looking into the Kitchen and Laundry room.  Garage in the front.
Laundry room was measured wrong!  We have to remove the closet that I was going to be putting my vacuum and cleaning supplies in. UGH


Great room looking into the kitchen.  Those structures are the end caps to our island.  (pic below is what it will look like but the color will match our cabinets)
**Love my corner Pantry!


The Island inspiration...



The cathedral ceiling






Friday, December 13, 2013

Framing on the Inside December 13, 2013

Dining Room:
Our half wall that got finished as a full wall but that they quickly fixed it.


Kitchen/Great Rooms:
Cathedral Ceilings


Outside Framing complete


Framing Complete with Concerns December 13, 2013

Framing complete.
We have some concerns on the inside regarding a few room sizes that we don't think are right.  Laundry, WIC and the Master Bathroom.  We are going to measure them Sunday. Then we will discuss with the Field Mgr on Monday.


Tuesday, December 10, 2013

The Framing Begins December 10, 2013

The temp today was in the 20's.  But with the windchill it was about 0 and 10 above!!!
Husband said the crew of 4 were working diligently.   





Monday, December 9, 2013

Wood Delivery Dec 09, 2013

They delivered the wood today and hubby will be staying the night in his truck because he heard a build in the area had a furnace stolen!!!!  The temps are in the teens and low 20's! 
Let's hope they get the framing complete quickly. Fingers crossed +




Friday, December 6, 2013

Waterproofing/Insulation Dec 6, 2013

One man job!


Orange is the insulation that was apply after the waterproofing was sprayed on.
Glass block located in the back of the house.


Notice some back fill was put in place.




Wednesday, December 4, 2013

Walls Poured December 4,2013

They got them done very quick. Tomorrow the forms will be taken off. 





Add caption



Tuesday, December 3, 2013

Truck Detained...December 3, 2013


They were supposed to start pouring the walls today.  Received a call from the field manager that the truck bringing up the forms for the walls got pulled over and detained.

Hopefully they will be back tomorrow!

Friday, November 15, 2013

WHY??? November 15, 2013

Hubby met the FM today at the house and discovered that some of the re-rods have been bent! And somebody took the frame and left the inside of the Wayne Home sign on the ground. REALLY??? I pray this is not a sign for things to come!  Hubby does not want to sleep there until it gets done.

I guess the rods will be able to get bent back but that is not the point!

Thursday, November 14, 2013






Wait For It....

Thursday November 14, 2013

They were suppose to be out today to start pouring the walls.  Got a text from our FM stating they wouldn't be able to start until Monday!  Would have been a great couple of days to do it before the cold front moves in.  Rain on Sunday!

This is me waiting since summertime for the house to be built.  The cutout is where the house is suppose to be!



Saturday, November 9, 2013

On Hold.... November 9, 2013

For another 5 days until the walls get poured.  So stayed tuned - hopefully I will be getting more progress pictures.


Tuesday, November 5, 2013

The Dig November 4, 2013

November 4th 2013

We all met at 8:30 am to get the ball rolling. 


  

Here is where the Egress Window will be.


November 5th 2013

Monday, November 4, 2013

Cheers November 4, 2013

Then we had to do a celebratory toast with Mimosa's.
Hubby, me, sister in law, brother in law, cousin (taking picture- the reason behind me holding 2 glasses).



Saturday, November 2, 2013

The Land


The Egress Window location

We purchased this piece of property in early 2013. Our scheduled dig date is Monday November 4, 2013.  How about that...my Birthday. What a great gift to receive.



Monday, August 12, 2013

Color Meeting 8/12/13

COLOR MEETING: August 12, 2013

Hand scraped wood for the entryway and kitchen.  Chiffon Maple cabinets and laminate floor for the Laundry room.


Main Bath and Master Bath Maple cabinets. I forgot to take a picture of the tile for baths. Cream colors.


White shutters,  Roof in shades of green/black, Cypress Creek Hemlock siding


Carpet selections in this video.


Kitchen/Laundry cabinets up close.